Bankable feasibility study: the checks a lender makes before relying on a study to approve a loan
🏦 Funding

Bankable Feasibility Study: What Lenders Check, With an Example

A feasibility study is bankable when it is detailed, evidenced and objective enough that a lender will rely on it to decide how much to lend and whether to approve the loan. In practice that means the forecast cash flow covers the loan repayments with room to spare, every part of the project cost has a confirmed source of money, and the numbers still repay the debt when things go worse than planned.

SimpleFeasibility Editorial Team · Updated 2026-10-16 · 12 min read

What "bankable" actually means

"Bankable" is not a legal grade or a certificate. It describes a study that a lender can use as part of its credit decision without redoing the work. A plain feasibility study answers the owner's question: is this worth doing? A bankable study answers the lender's question: if we lend this amount, on these terms, will we be repaid, even if things go wrong?

That shift changes the content. The lender cares less about the upside and more about how reliable the cash flow is, who carries each risk, and whether the evidence behind each assumption can be checked. A study written to persuade, with optimistic forecasts and no downside case, is the opposite of bankable, however polished it looks.

The term has two common uses. In small-business and commercial lending it simply means a study good enough to support a loan application, for example to a bank, the SBA or USDA. In mining and large infrastructure, "bankable feasibility study" (BFS) refers to the most detailed study stage, with defined cost accuracy and reporting rules. Both are covered below, starting with what lenders check in any sector.

What lenders actually check

1. Cash flow covers debt service, with a margin

The core test is the debt service coverage ratio (DSCR): operating cash flow divided by the principal and interest due on all business debt, including the new loan. A DSCR of 1.00x means every dollar of cash goes to the lender, with nothing left for a bad month. Lenders want a cushion above that.

A simple illustration: if a business forecasts $180,000 a year of cash available for debt service and its total loan repayments are $150,000 a year, its DSCR is 180,000 ÷ 150,000 = 1.20x.

The minimum depends on the lender and the type of loan:

Show the DSCR year by year, not just on average. A lender will look hardest at the first two years, when revenue is still ramping up and the loan payments are already due.

2. Sources and uses that balance, with no unfunded gap

A sources and uses table lists every cost needed to get the business running (the uses) and every source of money that will pay for it (the sources). The two totals must match. Uses should include the items owners often leave out: working capital for the ramp-up period, pre-opening wages, fees, deposits, interest during construction and a contingency. Sources should name each lender, each equity contributor and the status of each commitment. If the table only balances because of money that is "expected" but not committed, the lender will treat it as a gap.

3. Enough equity from the owner

Lenders want the owner to have money at risk. For SBA 7(a) loans to a start-up (a business that has been operating for one year or less), SOP 50 10 8.1 treats an equity injection of at least 10% of total project costs as necessary. Debt counts as equity only if it is on full standby, meaning no principal or interest is paid during the term of the SBA loan. Changes of ownership have their own equity rules in the SOP's appendix. Other lenders set their own levels, often higher for riskier projects, so ask early.

4. A cost estimate accurate enough for the stage

A lender cannot rely on a study whose capital cost could easily be 50% higher. Engineers describe estimate accuracy using the classes in AACE International's Recommended Practice 18R-97, written for the process industries. Its typical ranges, at an 80% confidence level, are:

AACE classTypical purposeLow rangeHigh range
Class 5Concept screening−20% to −50%+30% to +100%
Class 4Study or feasibility−15% to −30%+20% to +50%
Class 3Budget authorisation or control−10% to −20%+10% to +30%

AACE stresses that the actual range for any project depends on its technical complexity, the quality of the cost reference data, how well the project is defined and whether the contingency properly reflects the risks. A repeat project with good cost history can be estimated more tightly than a first-of-a-kind one. For a small business the same idea applies in simpler form: replace rough allowances with written quotes, signed lease terms and supplier price lists before you take the study to a lender.

5. Sensitivity analysis and a downside case

Every forecast is wrong to some degree. A bankable study shows by how much it can be wrong before the loan is at risk. At a minimum, test the DSCR against lower revenue, slower ramp-up, higher operating costs, higher capital cost and higher interest rates, one at a time and then together in a realistic downside case. State the break-even point: the revenue level at which cash flow just covers debt service. A lender will often run its own base case, usually more conservative than yours, so make it easy for them to change the assumptions.

6. Independent review

Larger lenders do not take the owner's study at face value. In project finance the lender usually appoints an independent engineer or lender's technical adviser, who reviews the technology, design, expected output, construction and operating contracts, permits and the assumptions in the financial model before financial close, then monitors construction and certifies drawdowns. In small-business lending the review is lighter, but SBA's SOP lists independent studies and reports (feasibility studies, hospitality facility assessments, energy audits and franchise assessments) as ways to offset weaknesses found in the credit analysis.

7. Market evidence a lender can verify

Revenue is the assumption lenders challenge most, so tie it to evidence: local demand data, competitor locations and prices, comparable businesses, signed letters of intent, pre-orders, or an existing customer base. Explain how each number was built, for example covers per day × average spend × trading days, rather than presenting a single total. Our guide to financial feasibility covers how to build the projections themselves.

Normal vs bankable feasibility study

Normal feasibility studyBankable feasibility study
Main questionIs the idea worth pursuing?Will the loan be repaid, even in a downside case?
Who commissions itUsually the owner, for an internal decisionThe owner, but written for a lender; sometimes prepared or reviewed by an independent party the lender accepts
IndependenceOften the owner's own viewAssumptions checkable by a third party; independent review where the lender or programme requires it
Cost estimateAllowances and benchmarksQuotes, contracts and, on engineered projects, an estimate class suitable for budget authorisation
FinancingTotal cost and return on investmentSources and uses, loan terms, DSCR by year, equity injection
RiskA list of risksSensitivity tests and a downside case run against the lender's covenants
OutputA recommendationA recommendation plus the numbers a credit committee needs to size and approve the loan

What "bankable" means in mining

In mining, the stages of study are tied to reporting codes, and "bankable feasibility study" usually means the final, feasibility-level study on which construction finance is raised. There is no single international accuracy standard, but the main codes are close to each other:

An example of a published mining BFS is Dateline Resources' Colosseum gold project in California, released on 11 May 2026. The company reported a pre-tax NPV (5% discount rate) of US$785 million and a pre-tax IRR of 49.5% at a gold price of US$4,200 an ounce, with start-up capital of US$249 million plus US$25 million contingency. These are company-reported, pre-tax figures from the study announcement; lenders will form their own view through their technical advisers. For the cost and risk side of mining studies, see our mining feasibility study guide.

SBA, USDA and project-finance rules, stated correctly

SBA 7(a) and 504

No SBA rule requires a feasibility study for every loan. The regulation is permissive: SBA "may require" professional appraisals, a survey or a feasibility study as a loan condition (13 CFR 120.160(b)). SOP 50 10 8.1, which governs applications that receive an SBA loan number on or after 1 October 2026, says SBA may request a study where it needs to understand the business type and local market better, and lists triggers such as:

Even when it is not required, a well-evidenced study helps: it is where the projections, assumptions, sources and uses and equity injection that the lender must analyse are set out in one place. For an SBA application, see what an SBA loan feasibility study should contain.

USDA Business & Industry and similar guaranteed loans

USDA is stricter. Under 7 CFR 5001.306, a guaranteed loan of more than $1 million to a new business requires a feasibility study prepared by an independent qualified consultant acceptable to the agency, with the scope set by USDA according to the complexity of the project and borrower. USDA may also require a study on other loans when the lender's analysis or the business plan is not enough to judge technical, market or economic feasibility. The regulations define a feasibility study as covering economic, market, technical, financial and management feasibility, and a qualified consultant as an independent third party with the knowledge, expertise and experience for the task.

Project finance and the Equator Principles

Many international banks follow the Equator Principles (EP4) for environmental and social risk. They apply to project finance where total project capital costs are US$10 million or more, and to some project-related corporate loans of US$50 million or more. Under Principle 7, an Independent Environmental and Social Consultant reviews the assessment for all Category A projects and, as appropriate, Category B projects. If your project is in scope, the lender will expect the feasibility study and the environmental and social assessment to line up.

What a bankable small-business study looks like: a real example

The example below is a study our system produced from a sample founder brief, run through the product exactly as a customer would. Every figure comes from its financial model; nothing was edited by hand. The brief: a mobile dog-grooming van in Plano, Texas, run by an owner-operator groomer with six years' salon experience, priced at about $95 for a medium-dog groom, with a capacity of about 6 grooms a day, 5 days a week. The founder planned to fund it with $35,000 of savings and a $60,000 equipment loan over 5 years at 9%.

The verdict, first

The study opens with a computed verdict, not an opinion: feasible if restructured. The business itself works (a 30.5% EBITDA margin once trading settles), but the plan as funded is $14,195 short. It needs $49,195 of the owner's money alongside the loan, against $35,000 available. That single condition is the first thing a lender reads, and it is stated with the arithmetic behind it.

Sources and uses that show the gap instead of hiding it

UsesAmountSourcesAmount
Van, grooming conversion and set-up$81,360Owner's own money (as stated)$35,000
Contingency$6,102Bank loan$60,000
Opening working capital$10,000Funding gap: still to raise$14,195
Cash to carry the ramp-up (lowest month)$11,733
Total funding needed$109,195Total once the gap is raised$109,195

The line most owner-written plans leave out is the ramp-up cash: the monthly cash flow shows the bank balance at its lowest in month 6, $11,733 below the opening position, before the business pays its own way. A plan that funds only the van would run short in the first half-year.

Loan cover year by year, and how much it can absorb

Year 1Year 2Year 3Year 4Year 5
Debt service cover (DSCR)2.18x2.26x2.71x2.55x2.82x

Annual repayments are $14,946. The lowest cover, 2.18x in year 1, is well above a 1.25x covenant. The study then asks the lender's next question: how far can sales fall before that changes? From year 2, sales can fall 16% before cover drops below 1.25x, and 19% before it drops below 1.0x. It also states the largest loan the cash flow supports at 1.25x, about $108,268, so the founder can see that a larger facility is serviceable if the equity cannot be found.

Capacity, and the market, set the sales line

Sales are held to what one van can physically do: 6 grooms a day, 5 days a week, 50 weeks a year, or 1,500 grooms. Year 1 sells 1,125 while the round fills, rising to 1,410 by year 5, and the study cautions that growth beyond 95% of the van needs a second van or groomer, which the plan does not include. It also flags the other limit: year-2 sales of $135,265 are 27% above the obtainable share its market research supports ($106,875 a year), and selling only that share would mean 21% lower sales, more than the 16% the loan cover can absorb.

The evidence it says to collect next

The study is honest that it rests on desk research and the founder's brief: demand and price have not yet been tested with customers. It then says what would settle them, in the model's own figures:

What the lender gets

Every chapter quotes that one model: a figure the model did not produce is not printed. That consistency, more than any single number, is what makes a study bankable.

Read the full study, its financial model and its investor deck (view only).

Common reasons lenders turn a study down

Bankable feasibility study checklist

  1. A one-page summary: the project, the loan requested, the DSCR, the equity, and the main risks.
  2. Market evidence for every revenue line, with the calculation shown.
  3. Operating costs backed by quotes, leases, wage rates and supplier terms.
  4. Capital costs from quotes or an engineering estimate, with a stated contingency.
  5. A sources and uses table that balances, with the status of each source.
  6. The owner's equity injection, its source, and proof that funds are available.
  7. Monthly projections for the first year and annual projections for at least the loan's early years: profit and loss, cash flow and balance sheet.
  8. DSCR by year against the lender's minimum.
  9. Sensitivity tests and a combined downside case, with the break-even point.
  10. Management experience and who runs the business day to day.
  11. Permits, licences and key contracts, with their status.
  12. Risks and how each is mitigated, including what the owner will do if sales come in low.
  13. Where required, independent review or an independent consultant's study.

For a step-by-step guide to writing each section, see how to write a feasibility study, and for the overall structure, our complete guide to feasibility studies.

Frequently asked questions

What makes a feasibility study bankable?

A study is bankable when it is detailed, evidenced and objective enough that a lender will rely on it to decide how much to lend and whether to approve the loan. In practice that means cash flow that covers debt service with a margin, a sources and uses table with no unfunded gap, a cost estimate accurate enough for the project stage, a downside case that still repays the loan, and assumptions that an independent reviewer can check.

Does the SBA require a feasibility study for a 7(a) loan?

Not as a rule. The regulation says SBA may require a feasibility study (13 CFR 120.160(b)). SOP 50 10 8.1, effective 1 October 2026, lists situations that may lead SBA to request one, such as market saturation, a unique market concept, a highly specialised property, or a project that is large for the community it serves.

What debt service coverage ratio do lenders want?

It depends on the lender and the loan. For SBA 7(a) loans, SOP 50 10 8.1 sets a minimum of 1.15 to 1, with 1.25 to 1 for initial acquisitions and owner buyouts and 1.10 to 1 for most 7(a) Small Loans. Project-finance lenders commonly size debt at roughly 1.20x to 1.35x, but these figures are indicative and vary by sector and contract strength.

When does USDA require an independent feasibility study?

Under 7 CFR 5001.306, a guaranteed loan of more than $1 million to a new business requires a feasibility study by an independent qualified consultant acceptable to the agency. USDA may also require a study on other loans when the lender's analysis or the business plan is not enough to judge technical, market or economic feasibility.

What is a bankable feasibility study in mining?

In mining, bankable feasibility study usually means a study at the final, feasibility level of the reporting codes. Under the US SEC rules in Regulation S-K 1300, a feasibility study has cost accuracy of about ±15% with contingency of no more than 10%, against ±25% and no more than 15% for a pre-feasibility study.

Can I write a bankable feasibility study myself?

For a small-business loan you can prepare most of it yourself, provided every assumption is backed by evidence such as quotes, leases, market data and comparable businesses. Some lenders and programmes then want an independent review or a study by an independent consultant, for example USDA guaranteed loans over $1 million to new businesses and lender-appointed technical advisers on project finance.

Sources

See your own numbers before you commit

Describe your idea in a sentence — what, where, how big, what budget. In about two minutes you get a revenue estimate and a market read, then the full Professional study is generated for you to preview free.

See what's included

No card, no account to start. Full studies with financial projections, NPV/IRR, competitor analysis and an Excel model from $149.

Related articles